Parties
Customer
Kevin Smith
205 Nathaniel Ct
Montgomery, Texas
Contractor
Jordan Marine Construction LLC
4950 Lazy Lane
Montgomery, TX 77316
Managing Partner: Chris Kick
1810 Eagles Cove, Friendswood, TX 77586
$7,000.00
Project Total
THRU FLO
Step Treads
Angle Iron
Mounted Frame
50% / 50%
Signing / Completion
Scope & Pricing
Custom stair build with 3×12 treated stringers on an angle iron frame, THRU FLO step treads, and railing per customer specification. Open-riser design (no risers). A $1,500.00 discount has been applied below.
| # | Description | Amount |
|---|---|---|
| 1 | Custom Stair Build Supply and build one (1) set of stairs with 3×12 treated stringers, mounted on an angle iron frame. Open-riser design (no risers). | |
| 2 | THRU FLO Step Treads Supply and install THRU FLO drainage step treads. | |
| 3 | Railing Supply and install railing as specified by the customer. | |
| Project subtotal | $8,500.00 | |
| Discount (credit) | -$1,500.00 | |
| Project Total | $7,000.00 | |
Payment Schedule
Payment is split 50% due at signing and 50% due on completion, based on the $7,000.00 project total.
| # | Milestone | Amount |
|---|---|---|
| 1 | Payment #1 — Due at Signing 50% deposit to schedule work and order materials. | $3,500.00 |
| 2 | Payment #2 — Due on Completion Remaining 50% balance upon completion. | $3,500.00 |
| Total | $7,000.00 | |